Stanley Street Construction - Sunset Drive to William Street

Update on Construction

 

Schedule:

 

The contractor’s schedule has been advanced. Construction will now begin on Wednesday, July 26, 2017.

 

Work scheduled for next week:

·        Mobilization and Temporary Traffic Control

·        Pulverizing the roadway from Sunset Drive to Wellington Street

·        Start watermain installation from Sunset Drive to Wellington Street

 

Road Closures:

 

The following streets will be closed to through traffic during construction:

·        Stanley Street from Wellington Street to Sunset Drive

·        Gladstone Avenue from Metcalfe Street to Stanley Street

·        Drake Street from Isabel Street to Stanley Street

·        Margaret Street from Victoria Street to Stanley Street

·        Victoria Street from Margaret Street to Stanley Street

Local traffic will be permitted wherever possible. Driveway access may be interrupted periodically during construction. The contractor will provide driveway access whenever possible.

 

Water shut-downs:

 

·        Short duration watermain shut-downs are anticipated when connections are being made to the new watermain.

·        If you will be affected by this work, a notice in this regard will be delivered to your property.

·        Unplanned water shut-downs may occur as the contractor performs work near the old watermain.

 

Safety:

 

·        Please use caution when using the street, and maintain a safe distance from any moving equipment.

 

For more information about this project and other construction projects in the City, please visit the City website and click on  Construction in the bottom right corner.

 

Your patience and understanding is greatly appreciated as we improve your street.

Monday, July 24, 2017